092 - San Diego Civic Theater
|
The Challenge: Avoiding the prohibitive cost and time-consuming abatement method of scraping and replacing the 19,000 square feet of Asbestos containing acoustic ceiling material throughout this downtown landmark building. |
|
|
Benefits Desired:
|
|
|
Results: The cost effective Class A Fire-Rated GLOBAL Encasement System that was designed allowed the contractors to complete the job in the shortest time possible while saving the building owners 5-6 times the cost of removal, disposal and replacement. The system included PrepLESS Primer™ to lock down any loose ceiling material followed by AsbestoSafe® TopCoat.
|
|